Laurence Calvert Academy, Leeds
Our Facades Division completed their impressive works on the £19.2 million / 1,050 place new build secondary school in Middleton, Leeds known as the Cockburn Laurence Calvert Academy. Works began back in June 2022 and the project completed on time to support Algeco UK‘s handover to the client in August 2023, ready for the new term.
Here is a reminder of what our team installed:
~ 1488m2 of 175mm Eurobond Rainspan Structural Panel
~ 1961m2 of 120mm MFS Insulation,1243 m2 of Rockpanel Rainscreen Cladding
~ 1000m2 of Norclad Western Red Cedar Cladding
~ 650m2 of Corium Brickslip System
~ 515m2 of Euroclad 32/1000 Trapezoidal Sheet Cladding
~ PPC Aluminium trims & profiles
~ 4000Lm of Firestopping
It is note worthy that through the Department for Education output specification the new school has achieved an equivalent of a Very Good BREEAM rating.